A high slump test indicates:

Study for the California General Contractor B Exam. Engage with multiple choice questions and flashcards, each offering hints and explanations. Prepare thoroughly for your test!

A high slump test indicates that the concrete mix has too much water in relation to the amount of cement and aggregate. The slump test measures the consistency and workability of the concrete mix. When the slump is high, it means that the mix has a loose consistency, which typically results from excess water. This can lead to a reduction in strength and durability of the concrete once it sets. In concrete, there is an optimal water-to-cement ratio that must be maintained to ensure proper curing and performance, and a high slump suggests that this ratio has been exceeded, potentially causing problems in the finished product. Hence, the assessment of a high slump being indicative of too much water is crucial for achieving the desired quality in construction practices.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy